By Anthony Capaccio
November 2, 2016 — 5:00 AM EDT Updated November 2, 2016 —
5:27 PM EDT
·
Pentagon officials says funds to be requested in next budget
·
Testing director ‘very strongly’ urges restructuring program
The Pentagon will need as much as $530 million extra to finish
the development phase for Lockheed Martin Corp.’s F-35, the most expensive U.S.
weapons system ever, defense officials said.
The F-35 program office made the request for
more money to complete development, which is supposed to be in its last stretch
after 15 years, during a closed-door review last month by the Defense
Acquisition Board, according to the officials.
The Defense Department and the military
services that are counting on the three versions of the F-35 are assessing how
to pay for a request that would go into the department’s fiscal 2018 budget
proposal. Approving the added funds would probably be the first F-35 decision
to reach the desk of the next defense secretary.
The call for more money comes as the
Pentagon’s chief weapons tester has issued a fresh warning that the aircraft,
projected to cost $379 billion for a fleet of 2,443 U.S. planes, is far from
showing it has full combat capability.
In an eight-page memo dated Oct. 14 and
obtained by Bloomberg News, Michael Gilmore, the director of operational
testing, recommended “very strongly that the program be restructured now and
provided the additional resources it clearly requires to deliver its
long-planned and sorely needed full” capability.
The majority of the added $530 million “will
be used to complete development flight tests” that are expected to be completed
by October 2017 and operational combat testing in fiscal 2018 and 2019, Joe
DellaVedova, spokesman for the Pentagon’s F-35 office, said in an e-mail.
He said $265 million of the $530 million is to pay for “unforeseen
delays,” and none of the funds will be required in the current fiscal year.
Kendall Disappointed
While the added $530 million would be a
fraction of what’s already a $55 billion development phase, Frank Kendall, the
undersecretary of defense for acquisition, said in an e-mail that he was
“disappointed to hear that additional funds would be needed” and “we are
working to minimize the size of the shortfall and to deliver options to address
it.”
Pentagon Comptroller Mike McCord said he
“wasn’t totally shocked” by the funding request. While it’s not a big increase
considering the size of the program, McCord said in an interview, “I was
hopeful, maybe, that we wouldn’t have a problem like this because” the program
“has been moving in a fairly decent direction.”
DellaVedova said “most of this needed funding
will come from other F-35” funding sources “to minimize the impact on the U.S.
Services and DoD overall budget requirements. No additional funding will be
required from the international partners” who are buying the plane. The U.K.,
Italy and Australia are among those buyers.
The F-35 is being developed even as the plane
is in low-rate production, an overlap that Kendall once called “acquisition
malpractice.” The request for more funding is at odds with past assurances that
the program would absorb any cost increases in development.
“In the development program we like to tell people that we have
no more money and we have no more time,” Air Force Lieutenant General
Christopher Bogdan, director of the Pentagon’s F-35 program office, said at a conference in 2014.
The program had “the resources to complete” on
time and “on budget, and we intend on doing that,” he said then. “We don’t plan
on going back and asking for any more money or any more time to get this
program done.”
Development Extended
The development phase was originally scheduled
to end in fiscal 2012. That was extended to fiscal 2016 during a major program
reorganization in early 2010, and $476 million in funding was added then.
Gilmore, the testing director, said in an
e-mail that he estimates flight testing required to complete the development
phase won’t be finished until November 2018, at least a year later than
planned, “unless the program is allowed to skip/delete planned” evaluations.
In Gilmore’s memo, he cited
issues including a 10-month delay to December in the release for flight testing
of the latest version of the F-35’s most capable software; insufficient
progress in flight testing of combat mission systems; questions about design
deficiencies with the plane’s gun; too few aircraft available for flights; and
as many as 1,179 “significant open” software deficiency reports.
‘Limited Progress’
Gilmore said the program has made only
“limited progress” since he wrote Pentagon leaders Aug. 9 expressing concerns a
week after the Air Force declared its version of the F-35 operational.
Air Force Secretary Deborah James certified to
Congress in September that aircraft scheduled to be delivered starting in early
2018 will be fully combat-capable, but Gilmore said in a separate e-mail
Tuesday that he considered that unlikely.
In his memo, Gilmore wrote that the F-35 can’t
be ready for the combat testing it needs to pass before the aircraft can be
deemed ready for full-rate production “if it is unwisely constrained to operate
within its currently planned budget and schedule.”
The program needs more funding, Gilmore said,
to “complete all the testing” needed “to rectify a substantial number of
existing critical deficiencies as well as the new deficiencies that will
inevitably be discovered.”
Original post: bloomberg.com