Saturday, 24 November 2018

Severnaya Verf and Sredne-Nevsky Shipyard agreed on payment schedule for the manufacture of composite superstructure for lead corvette project 20386

One of the variants of the appearance of the corvette project 20386 - RusArmy.com


Igor Ponomarev: The issue of payment of the composite superstructure for the corvette "Daring" resolved


November 21, 2018 

Severnaya Verf and Sredne-Nevsky Shipyard agreed on a payment schedule for the manufacture of a composite superstructure for the head corvette of the project 20386 Daring. About this Mil.Press FlotProm said the general director of the "Severnaya Verf" Igor Ponomarev. On November 8, the publication reported a delay in work due to late financing.

“Indeed, we had a delay in financing the work on the superstructure for Derzkoy,” Ponomarev told the publication. “But now these issues have been resolved. The Ministry of Defense has allocated funds to continue construction of the project 20386 corvette. add-on payment. " 

The general director of Severnaya Verf added that the first tranche has already been completed in accordance with the previously reached agreements, and some of the work will be paid before the end of 2018. Subsequent payments are scheduled for 2019.


“We are carrying out planned work on the corvette: the building and assembly shop of the Northern Shipyard has completed cutting the metal of the main hull structures, the workers are now assembling the bottom sections of the first block of the ship. The berth workshop has finished assembling the outer casing of the second block, continues to form internal fences and decks,” said Igor Ponomarev on the construction of the "bold".


According to him, in late November and early December, the plant will begin to form the hull of the ship. 

A specialist in composite materials from the Krylov State Research Center, who is familiar with the situation, told Mil.Press FlotProm that problems can be associated only with late payment, and not with the technical side of the issue. According to him, the SNSP has mastered and worked out all the necessary technologies, the shipyard is already preparing a snap for molding the elements of the superstructure, in particular its sides and walls. 

Help Mil.Press FlotProm

The contract for an integral part of the development work for the manufacture of a composite superstructure for the head corvette of the new project “Severnaya Verf” and the SNSP were concluded in March 2018. As described at the Sredne-Nevsky Shipbuilding Plant in response to a request for publication, the technological period for the preparation of production (manufacturing of special technological equipment) for the design features of the project is six months, the construction of the superstructure itself is 20 months. 

Thus, it is possible to complete the manufacture of the superstructure in May 2019. However, the deadline was transferred to the right, according to preliminary data - at the end of 2019. At the same time, the SNSP does not exclude the possibility of reducing the technological cycle under the condition of uninterrupted funding, the plant’s press service told Mil.Press FlotProm. 

The head corvette of the project 20386 "Daring" was laid September 28, 2016. It is planned to be launched in May 2021. 

Dmitry Zhavoronkov 

Source: flotprom.ru

Related article:
Lead ship 'Derzky" Project 20386 plan to be launched in 2021

PROJECT 20386 (CORVETTES): Details