Wednesday 28 November 2018

ITS Antonio Marceglia Completes Sea Trials

ITS Antonio Marceglia - OCCAR photos


September 27, 2018 – The Fourth Italian General Purpose ship and the eight Italian FREMM to be delivered, ITS Antonio Marceglia finished its sea trials on the 20th of November after the completion of all tests foreseen for the Platform and Combat System equipment.

As occurred last year for ITS Martinengo, ITS Antonio Marceglia have completed sea trials in only five months after the First Sea Going in last June, confirming the strong coordination existing between all the actors involved in the program (NAVARM/UTNAV, IT Navy, FREMM PD, and Industry). Indeed, in each of the thirteen scheduled sea trials, the effective coordination of all stakeholder played a key role in order to complete all trials on schedule although the activities at sea were challenging, with different GFx (at least ships, airplanes and helicopters).

Starting from ITS Alpino, delivered to the Italian Navy in 2016, the “Zero ANT” (Activities Not Terminated) objective requested by Italian Navy is the goal to be accomplished. In order to take this achievement through in line with the contractual schedule, the Final Official Acceptance of ITS Antonio Marceglia is scheduled on the next 16th of April.

Source: seawaves.com

Related article:

Bergamini class (FREMM) frigate: Details

No comments:

Post a Comment